Queens Wharf Tower to be laid to rest

29 Aug 2018

A new more aesthetically pleasing era will dawn on Newcastle's skyline on Monday 17 September following the removal of the now-redundant Queens Wharf Tower.
 
Long derided by locals and tourists alike for its dubious shape, the tower will be painstakingly disassembled and removed in a challenging operation in the early hours of that morning and subsequent days. 

Mayfield-based contractor Major Projects Group (MPG) successfully tendered for the job and will deploy metallurgists and dog crews to detach the top dome and observation deck on the first night of removal work.

MPG aims to lower the most prominent parts of the tower to the ground with a giant crane before detaching and lowering two sections of the spiralling-steel stairwell encasement before the sun comes up. 

To see an animation of the removal operation, click here

"Novocastrians will wake to a conspicuous absence on the skyline the morning of 18 September," Lord Mayor Nuatali Nelmes said. 

"When the first of a record 20 cruise ships calls the port in October to begin the season, passengers will enjoy an uninterrupted view of the city's 19th and early 20th century architectural splendour. 

"Removal of the tower, which was originally only intended to stand for two years, will save Council and rate payers around $1.6 million in maintenance costs over the next four years. 

"While it does have a place in our history, it's long been the subject of ridicule and is well outdated in terms of accessibility for those with mobility challenges. 

"For those who want one last go at a climb, there is still time until Sunday afternoon." 

MPG will remove two more pieces of the tower, lower roof and the walkway over the following two or three nights, before the lower deck and remaining section are lifted out early on Friday 21 September. 

"The major challenges of this project are working next to a busy pedestrian area and street, as well as close to occupied tenant space," MPG Project Manager Peter Allen said. 

"We will remove each section using a 300-tonne crane, and all major work will be completed on night shifts to avoid any disruption to the daily life of the public enjoying the wharf area." 

Following the removal, City of Newcastle will install synthetic grass, coloured rubberised surfaces and raised tree planters with seating to activate the site. Alexander Palms similar to those along the foreshore will be planted later in the year. 

"This is a temporary solution for place activation with an anticipated life-span of up to five years," the Lord Mayor added. 

"A permanent solution for the area will be addressed in the master planning for the whole Foreshore, which will include community consultation." 

MPG will start setting up temporary fencing, pavement protection, hoarding and site accommodation on Monday. 

The project will be carried out at night to allow a crane to park on Wharf Road and to minimise disruption to surrounding businesses. 

Neighbouring residents have been notified about the proposed night time works and have until 10 September to make a submission.

For interviews call 4974 2264 or let me know by return email.