Shortland Esplanade embankment stabilisation

HeroImage

We are improving public safety by restabilising two sections of the embankment along Shortland Esplanade (below Fort Drive) near Nobbys Beach kiosk (Swell Cafe) and opposite the Cowrie Hole. 

Map showing Shortland Esplanade and locations of embankment stabilisation.
This project will start 15 July at the northern site and will be delivered in two stages. The contractor will then move to the southern site early August (pending weather). 

What does the work involve?

Stage 1 will involve 'soil nailing' in both locations to reinforce the embankment ahead of Stage 2, construction of retaining walls. 
 
This project will deliver the following improvements: 

  • Increased stability of affected sites with soil nailing to reinforce and strengthen the existing embankment 
  • Construction of new concrete piled retaining walls to stabilise the embankment 
  • Revegetation along the embankment to help with sediment control 
  • Improved stormwater controls to reduce the risk of future landslips. 

Project details:

  • Construction will be between 7am - 6pm weekdays.
  • Traffic management and signage will be in place. 
  • There will be Increased truck movements in the area.