Timing | Works |
September 2020 | Site establishment by contractor |
November 2020 | Removal of light towers |
November to December 2020 | Bulk earthworks |
January to March 2021 | Blended soil prepared for use on playing field Installation of new drainage |
April to May 2021 | Installation of new irrigation system |
April 2021 | Installation of new light towers |
May to June 2021 | Construction of new cricket wickets |
May to June 2021 | Installation of new playing field perimeter fencing |
July 2021 onwards | New turf laid |
December 2021 | New turf established |
October 2022 | No. 1 Sportsground reopened for use |